Major Haverhill Main Break Forcing All of City’s Sewage into Merrimack; Fix to Take Several Days

Haverhill wastewater treatment plant, 40 S. Porter St., Haverhill. (Courtesy photograph.)

Most of Haverhill’s sewage is flowing into the Merrimack River, and will be for a few days, as the city deals with Friday night’s failure of a critical concrete main that dates back to the 1970s.

Public Works Director Robert E. Ward told WHAV the break was triggered by torrential rains and the city had an emergency contractor on-site within hours. He said all required notifications were filed with state and federal environmental agencies. Combined sewer overflow information was also reported on the city’s dedicated website.

“Our 42-inch force main, that goes from our main pump station to the plant, failed. So, that’s most of the city’s wastewater flow goes through the stage of the plant,” he said.

Ward estimated a range of seven to 10 million gallons a day is flowing into the river. That’s the entire city flow, not counting any added rainfall. As the situation stands now, Ward said, a contractor, Xylem, will spend the next few days installing a temporary bypass line. He said Xylem helped the city back in 2023 with a major Washington Street pipe collapse that caused effluent to flow down to River Street and projects dating back 20 years.

A second contractor will also be involved getting to another break several hundred feet up the line from the first. He said contractors can lay down a thousand feet of pipe a day and he expects initial work will last at least three to four days.

“The number one goal is to stop the sewage flowing into the Merrimack River. That’s the number one priority,” he explained.

Ward said the city is also making calls in search of pipe and fittings—a process made more complicated by outdated concrete pipe. Haverhill will likely have to use ductile iron pipe and find fittings to adapt it.

Mayor Melinda E. Barrett and Inspectional Services Director Richard MacDonald also went to the site get an understanding of the situation.

While untreated sewage is flowing into the river downstream from Haverhill’s downtown, Ward said, the city is somewhat spared that it is not flowing into streets or a neighborhood or causing private property damage.

The effect immediately became clear downriver as Newburyport said Saturday Plum Island Beach would remain closed to swimming.

Public Health Director Kelechi Obika said the beach was close to reopening after Haverhill’s Thursday combined sewer overflow, but Friday’s “active discharge” brought the new swimming ban.

“This closure is being implemented out of an abundance of caution to protect public health while the discharge is stopped, repairs are completed, and conditions can be fully evaluated.,” Obika explained.