Those traveling along Interstate 495 over the next two weeks may face nightly lane closings between the Ward Hill and Methuen exits as preparation continues to replace northbound and southbound bridges.
State transportation officials say work involves roadway maintenance and repair work along I-495 and the Ward Hill Connector, known formally as Industrial Avenue, as well as earthwork operations within the highway medians. Lanes will close between exits 105 and 106, as needed, from 9 p.m. to 5 a.m., through Saturday, June 20.
Work is part of a $400 million project to replace the I-495 bridges as well as two east and westbound bridges on the Ward Hill Connector that will be replaced with a single bridge over I-495 in Haverhill. Current work, being undertaken by SPS New England/DW White Joint Venture, include bridge foundation installation and earthwork for the temporary median crossovers to support the first bridge construction.