Interstate 495 Restrictions Begin as Four Bridges to be Replaced Over Next Few Years

Rendering of planned Interstate 495 bridges over the Merrimack River between Haverhill and Methuen.

Motorists will see overnight restrictions this week as early work begins to replace two Interstate 495 bridges between Haverhill and Methuen and two Ward Hill Connector bridges.

Up to two lanes will close nightly, beginning at 8 p.m., along I-495 southbound, between the Ward Hill and Route 213 exits, through 5 a.m., Thursday. The work is part of the nearly $400 million project to replace the north and south I-495 bridges over the Merrimack River as well as replacing two east and westbound bridges on the Ward Hill Connector, also known as Industrial Avenue, with a single structure over I-495 in Haverhill.

State transportation officials and representatives of the SPS New England/DW White Joint Venture gave a public overview Thursday night at Haverhill City Hall. Joseph Stasio, assistant construction engineer for alternative delivery, said rather than the conventional bid process where a design is completed and sent out to for construction proposals, the state creates a preliminary 25% design and takes combination design-build bids.

“The reason we do this is to encourage innovation and coordination between the contractor and their engineering partner with the goal of delivering a safe, high-quality project in a shorter timeframe and with lower costs,” he explained.

Stasio said the project extends 1.5 miles along 495 between exits 105, Route 213 in Methuen, and 106. Industrial Avenue work is limited to about a quarter mile while work along Merrimack Street in Methuen limited to about 650 feet under the highway. While the 1964-era 495 bridges are safe, he explained, they are at the end of useful life and do not meet modern standards.

When completed, Stasio continued, the new bridges will still accommodate three travel lanes in each direction and feature extra wide high-speed shoulders, some widening, a half-mile noise barrier along I-495 northbound to shield residential areas from highway noise and better lighting at the Industrial Avenue intersection.

Troy Thirkell, representing SPS New England/DW White Joint Venture, told those gathered what to expect.

“We do build a temporary work trestle over the Merrimack River. This staged sequence, and utilizing the temporary work trestle, allows us to build the bulk of the structure off the main highway,” he explained.

Construction of the new Ward Hill east-west bridge over I-495 will begin between the existing bridges, as Thirkell explains.

“Building a portion of the new Industrial Avenue overpass, From here, a slight traffic shift can take place, taking the westbound structure ouit of work. Therefore, we can then demo that structure and complete the rest of the Industrial Ave. bridge.”

Work on the I-495 southbound bridge begins first. During construction, traffic will be diverted over the median and bridges shared. Substantial completion is expected by the end of 2029 with restoration and cleanup early in 2030.

In the end, Stasio noted, I-495 bridges will be built with fewer joints; reduced future maintenance disruptions; improved height clearance to 16 feet, six inches; reduced number of bridge piers in the Merrimack River; reduced overall Ward Hill Connector bridge footprint; improved geometry and length of the exit 106 northbound offramp and deceleration lane to Industrial Avenue and allowance for future pedestrian and bicycle paths along Industrial Avenue and Methuen’s Merrimack Street.