Pfc. Ralph T. Basiliere, Haverhill’s first Vietnam War casualty, who was killed in action in 1966. (Courtesy photograph.)
(Additional image below.)
Haverhill’s new Pfc. Ralph T. Basiliere Bridge is now expected to cost up to $251 million and will be built over six years with work scheduled to begin this fall.
The Massachusetts Department of Transportation board last Wednesday awarded the design-build construction project to Littleton-based Middlesex Corporation and Kansas City, Mo. Transystems Corporation. The bridge carries Route 125 over the Merrimack River from downtown Haverhill to Bradford.
“Notice to Proceed is expected to be given to the winning Design-Build team late this summer, with construction anticipated to begin before the end of the year,” transportation officials said in a statement Friday. They added there will be an opportunity for the public to learn more at a planned introductory meeting.
The replacement structure will be slightly wider than the existing, 100-year-old bridge and feature two northbound lanes, two southbound lanes and a shared-use bicycle and pedestrian lane that will extend to 15 feet wide near proposed Merrimack River “overlooks.” It will continue to have familiar arches, including a separate span for crossing above the Bradford Rail Trail. As WHAV reported at the time, designers said in 2023 they included elements that pay homage to the 1925-era structure. Granite from existing piers will be repurposed to construct retaining walls along the Bradford Rail Trail and a copper roof, to be salvaged from an existing bridge tower, will be used on a proposed gazebo and kiosk adjacent to the trail.
Officials said pedestrian access to the Rep. Brian S. Dempsey Boardwalk in downtown Haverhill and Bradford Rail Trail on the other side is to be maintained throughout construction and restored at the end of the project.
Called, the “Best Value,” the Middlesex Corporation bid submitted July 2 was $215 million, with contingencies, engineering and other costs bringing the estimated total to $251 million. Salisbury-based SPS New England bid $264 million and Barletta Heavy Division bid $276.4 million, according to a MassDOT staff overview. Relocating utilities and the lack of an adjacent layout area were given as reasons for the job’s quarter-billion-dollar price tag. The City of Haverhill is also installing a new water main across the bridge.
The bridge will be constructed in two stages to keep traffic flowing.

Rendering of proposed overlook on new Pfc. Ralph T. Basiliere Bridge. (Courtesy).