A Clinton construction company starts work later this summer to cap the final section of Haverhill’s former landfill—the last step before the city builds new athletic fields there.
J. Bates & Son, the low bidder, was recently awarded the $14.4 million project to seal the so-called “north mound” of the former city dump. The south mound was capped several years ago and is now home to a solar energy farm. The state Department of Environmental Protection still must give its approval before work begins.
Capping the Old Groveland Road Landfill will prevent rainwater from leaching chemicals out of the refuse and polluting the adjacent Merrimack River, according to Haverhill Public Works Director Robert E. Ward. Once capped, two athletic fields will be constructed on top. The city is paying $7.9 million in a 50-50 split of the cost with the co-owner of the landfill, Amrize, formerly Aggregate Industries. Ward noted the city is paying the full cost of adding the athletic fields.
Ward added he expects construction will start later this summer and take two years. First the mount must be graded. Then an impermeable plastic sheet will be installed topped with a layer of sand and loam. Then the property will be seeded with grass.
“I am hoping the athletic fields will be ready in the fall of 2026, but spring 2027 is more likely,” Ward told WHAV.
The 71-acre property was operated as a city landfill for some 60 years—first opening after the Great Merrimack River flood of 1936 as a means of disposing of debris—and continuing through the mid-1990s. Household waste was phased out in the early 1980s but sludge from the city wastewater treatment plant was dumped there until 1996, Ward said. The landfill also accepted waste from the former Haverhill Paperboard company. The U.S. Environmental Protection Agency designated the property as a priority “Superfund” site in 1986.
As previously reported by WHAV, the city negotiated annual payments in lieu of taxes from Kearsarge Energy, the operator of the solar farm, as well as rent payments. The two payments total $2.7 million over a period of 20 years.
The city also has an agreement to buy electricity from Kearsarge at a discounted rate.
City said they had hoped to have the project completed three years ago, but Ward said “the lengthy process of environmental evaluation” pushed the timetable back.