The lack of southbound traffic last weekend over the Pfc. Ralph T. Basiliere Bridge in Haverhill helped speed the full installation of six of 16 beams at the span of the bridge over the Bradford Rail Trail.
Work is continuing this week, between 7 a.m. and 3:30 p.m., with a focus on completing the remaining beam installations. The bridge and sidewalks remain open, but traffic is subject to lane shifts. The Bradford Rail Trail, however, will remain closed where it passes under the bridge.
State transportation officials said Monday a total of 14 beams were placed, with welding completed on 12 of the 14, but they were not completely installed. The work is still not part of the planned replacement of the structure, but rather repairs to keep the bridge safe until it is replaced. Demolition of the existing century-old bridge over the Merrimack River between Haverhill and Bradford, and construction tentatively begins later this year. The new bridge, which will also carry Route 125, is still in the preliminary design stage. Massachusetts Department of Transportation officials said they are in the process of selecting a design/builder.
The bridge will close completely this coming Sunday, March 2, from 7 a.m. to 3 p.m., with all traffic detoured over the Joseph C. Comeau Memorial Bridge. This Saturday and Sunday, March 1 and 2, crews will work from 6 a.m. to 6 p.m. to complete any needed beam work. In case of inclement weather, work will be pushed to Sunday, March 9.
When the Basiliere Bridge reopens, however, drivers will find a new lane configuration, directing traffic towards the center of the bridge at the span between its towers. The new pattern is design to reduce stress on the bridge’s outer edges.