Healey Says Study Shows New Gas Pipeline is Not Needed

Pipeline map showing Haverhill loop.

Plans to boost local natural gas capacity by approving the Kinder Morgan pipeline received a thumbs down by Massachusetts Attorney General Maura Healey Wednesday.

Healey said a study commissioned by her office has determined that the region is unlikely to face electric reliability issues in the next 15 years and additional energy needs can be met more cheaply and cleanly through energy efficiency and demand response. The study was designed to, first, determine whether the region is facing electric reliability challenges through 2030 and, second, identify the most cost-effective and clean solutions for addressing any of those challenges.

“As we make long-term decisions about our energy future, it’s imperative we have the facts,” said Healey. “This study demonstrates that we do not need increased gas capacity to meet electric reliability needs, and that electric ratepayers shouldn’t foot the bill for additional pipelines. This study demonstrates that a much more cost-effective solution is to embrace energy efficiency and demand response programs that protect ratepayers and significantly reduce greenhouse gas emissions.”

The proposed Kinder Morgan fracked gas pipeline includes a portion which would pass through Andover and add a “Haverhill Loop.”

The study, conducted by the Analysis Group over the last three months and guided by a Study Advisory Group, found that through 2030 the region’s power system reliability will be maintained during our coldest winter months. The study used extremely conservative assumptions, including applying winter conditions from 2004 (one of the coldest years in two decades).

Analysts also modeled a worst case scenario under which New England becomes even more reliant on natural gas power than expected, and experiences a short-term disruption in other fuels, causing the electric system to be more stressed than expected on very cold days. Under those conditions, the study determined that the region could need roughly 2,400 megawatts for a few hours across nine very cold days by 2029 and 2030. That is the energy-equivalent of an additional .42 billion cubic feet per day of new gas capacity.

To solve that deficiency, the study evaluated several options including 1) reliance on incremental dual fuel-power plants (the status quo), 2) a higher reliance on firm liquefied natural gas (LNG), 3) incremental natural gas capacity, 4) energy efficiency and demand response, 5) energy efficiency and low-carbon imports on existing transmission, and 6) energy efficiency and low-carbon imports with new transmission. Solutions were compared to the status quo and evaluated for both their costs/savings for ratepayers and their impacts on New England’s greenhouse gas emissions.

The study concluded that all of the solutions would ensure the reliability of the electric system in a worst-case scenario. However, investment in energy efficiency and demand response would result in the greatest customer savings and would reduce greenhouse gas emissions. New gas pipelines would result in less customer savings and would actually drive up greenhouse gas emissions, Healey’s office said. Energy efficiency combined with firm low carbon imports on existing transmission lines would also save customers money and would produce the greatest reduction in GHG emissions.

The study accounted for recent news that Pilgrim Nuclear Power Plant is scheduled to shut down no later than June, 2019, resulting in the loss of 680 megawatts of non- greenhouse gas emitting power.

Healey provided a copy of the study to the Federal Energy Regulatory Commission for its consideration as part of the federal review of the Kinder Morgan Northeast Energy Direct pipeline project. The study was made possible by grants from the Barr Foundation and the John Merck Fund.

6 thoughts on “Healey Says Study Shows New Gas Pipeline is Not Needed

  1. This is an opportunity to allow Massachusetts residents, New Englanders and the Nation to be both self sufficient in energy sources via production as well as realizing long term costs savings for residents and businesses. Natural gas is a clean and efficient way to provide energy to this starved state.

    • I for one would be happy if my taxes helped communities install solar arrays and could subsidize costs for more needy families. Not everyone needs a personal installation. We need to think about new distribution models.

  2. Time to end fracking. The environmental impact is too high. Time to explore alternative and local energies and end the dependence on oil. Solar, wind, tidal are all abundant. Legalize hemp for industrial and energy purposes. Hemp is a rich source of new jobs for the area

    • At $40/bbl for oil fracking is finished, and we’re already seeing smaller companies associated with the industry go belly up. There is also nothing on the planet, for it’s size AND mobility that produces the amount of energy that oil does, at least not yet. Solar and wind have their own drawbacks as well, but no one wants to discuss those.